POWER7 information

BPR/BPD configuration

Use the below table to find out the requirements for Bulk Power Regulators (BPRs) and Bulk Power Distributions (BPDs) for a POWER7 I/O rack new build. Depending on the number of BPRs in your system, phase imbalance can occur in line currents.

Table 1. System BPR and BPD Requirements (POWER7 I/O rack new build)
Drawers BPRs BPDs
1 1 1
2 1 1
3 1 1
4 1 1
5 2 1
6 2 1
7 2 1
8 3 1
9 31 21
10 31 21
11 31 21
12 31 21
13 31 21
14 31 21
15 31 21
16 31 21

1 A higher rated line cord is required.