The goal of this exercise is to create sample activities
for the Inception > Inception Iteration [n] activity using
the activities in the Inception Iteration capability pattern from
Classic RUP.
About this task
Because we are only using a small subset of the activities
included in the Inception iteration capability pattern, we chose to
just copy those rather than copy the entire Inception Iteration capability
pattern and delete the ones we do not want. You may choose otherwise,
which we will demonstrate in the next step.
Procedure
- Make sure that the Configuration editor is still showing
the classic_rup_for_teamy delivery process. In the Work Breakdown
Structure, expand Classics RUP for Team Y >Inception. The editor panel should look similar to this:
- Change the current configuration to Classic RUP (for large
projects). Do this by using the configuration selection menu.
- In the Configuration view panel, expand Processes
> Capability Patterns > Classic RUP > Templates for Delivery Processes
> Inception Iteration. You will see a much longer
list of activities than we currently have for our new delivery process.
- Drag and drop the following activities from the Configuration view
to the Inception Iteration [n] activity in the new delivery
process :
- Develop Initial Vision
- Define the System
- Perform Architectural Synthesis
- Manage Iteration
- Plan for Next Iteration
A small menu opens with the choices to Copy, Extend,
or Deep Copy.
- Select Copy for each of the activities that you
are adding to the delivery process.
- Rearrange the relative sequence of activities in the Inception
Iteration [n]. To change the relative order of activities in the
Work Breakdown Structure, right-click an activity and select Move
Up or Move Down. For example, the Plan for Next Iteration activity
should be the last on the list.
- Create an activity diagram for the new Inception Iteration
[n] activity by right-clicking the activity name and selecting Open
Activity Diagram. The diagram is pre-populated with activities
from the Work Breakdown Structure. Refine the diagram so that it looks
like the following. Do not spend too much time making the diagram
look pretty. You can incrementally move elements by holding down the
Control key and clicking the Up, Down, Left, and Right Arrows.
Attention: Engineering Method Composer does
not automatically create synchronization bars. To get those, delete
all links in the diagram and redraw. You can select multiple links
at a time, right-click, and select Delete. The Fork Node and
Join Node tools can be used to create the synchronization bars.
- Rename the Inception Iteration [n] activity to Inception
Iteration, because we only plan to have one iteration in the inception
phase. You can rename an activity directly in the WBS by double-clicking
it and then changing it, or you can right-click the activity and select Show
Properties View, and then change the name field in that view.