IBM Support

PO Commit Timeliness

Question & Answer


Question

PO Commit Timeliness

Answer

PO Commit Timeliness

After a PO is sent to a supplier the supplier is expected to committo the order within a specified time period after the order is created.If an order is committed on time by the supplier then the KPI valueis 100 otherwise the KPI value is zero.

This KPI metric is computed based on the difference between theorder creation date and the committed date. The supplier is consideredreliable if the difference between the expected date and the actualdate is less than or equal to the configured number of hours.

If there are multiple commitments the first commitment is consideredfor the KPI metric.

The PO Commitment Timeliness KPI is computed as:

Percentage of orders committed on time = (Number of POscommitted on time / Total number of POs in that time period) * 100


"

[{"Business Unit":{"code":"BU055","label":"Cognitive Applications"},"Product":{"code":"SS73G6","label":"Sterling Total Payments for Financial Services"},"Component":"","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"All Versions","Edition":"","Line of Business":{"code":"","label":""}}]

Document Information

Modified date:
08 December 2018

UID

ibm10762039