Question

How to Reschedule an Existing Report

Answer

In order to reschedule a report created within Premium Reporting of Business Objects, you will need to complete the following steps.

1.? Locate the History of the given report. This is done by opening up the report in Design/Modify mode. In the top left corner, click on the History icon.

2.? In the History listing box that is brought up, locate the report that you wish to reschedule. Right click on the report.

3.? In the dialogue box that appears, click on More Actions and then Reschedule.

4.? At this time, the report schedule can be updated and saved.