PO Commitment Changed
Whenever a PO is placed suppliers send a commitment to the buyer. This alert is raised when there is a change in the committed quantity the committed dates or the committed price by the suppliers. This alert cannot be resolved automatically even if the variance in quantity date or price is solved because of subsequent commitments. The allowable discrepancy in the ship date delivery date quantity and price is configurable by the buyer organization for the suppliers.
Trigger Criteria for Raising the PO Commitment Changed Alert
Suppliers who send a PO Commitment are expected to commit the quantity within the committed date. The system raises this alert if the committed date quantity or price is different from the previous PO commitment date quantity or price as committed by the suppliers.
This alert is raised at the order line level.