Hardware requirements
Answer
Hardware requirements
There are no additional hardware requirements for deploying IBM? Work Optimization for Water Utilities as the productis installed on top of the existing servers in the IBM Intelligent Operations Center cluster. Howevera temporary IBM Work Optimization for Water Utilities installation management server meetingthe minimum hardware specification is required. This server is onlyrequired during the deployment process.
IBM Intelligent Operations Center hardwarerequirements
The hardware requirements of the IBM Intelligent Operations Center servers that IBM Work Optimization for Water Utilities is installedon top of are defined in the IBM Intelligent Operations Center Information Center.These are the minimum hardware requirements. The IBM Intelligent Operations Center cluster might requireadditional resources depending on any additional IBM Smarter Cities? Software Solutions that are deployedin this environment.
Installation management server hardwarerequirements
| Server Hardware | Minimum requirements |
|---|---|
| Number of processors | 2 |
| Processor type: | An x86 64-bit processor that must be oneof the following types:
|
| Memory | 8 GB |
| Hard disk | 80 GB |
- The /tmp folder on the IBM Work Optimization for Water Utilities installation management server servermust have at least 2 GB of available space.
- Define the swap space to be twice the amount of the physical memory.For example if a server has 8 GB memory define 16 GB of swap space.
IBM Intelligent Water clienthardware requirements
| Client Hardware | Minimum requirements |
|---|---|
| Monitor | 1280 x 800 resolution |
| Memory | 2 GB |
| Processor CPU | 2 Ghz |