Problem
Local Service Development Preferences are not working correctly in Designer.
The checkbox "Automatically reload IS assets after VCS operations" always stays disabled/enabled - depending on the value of "Move project to Integration Server package as linked resource".
To recreate in Designer:
1. Navigate to Window > Preferences > Software AG > Service Development > Local Service Development
2. Uncheck "Automatically reload IS assets after VCS operations" & "Move project to Integration Server package as linked resource"
3. Click Apply and Close
4. Navigate to Window > Preferences > Software AG > Service Development > Local Service Development ---> Both settings are correctly unchecked.
5. Check "Automatically reload IS assets after VCS operations" & leave "Move project to Integration Server package as linked..." unchecked
6. Click Apply and Close
7. Navigate to Window > Preferences > Software AG > Service Development > Local Service Development ---> "Automatically reload IS assets after VCS operations" is wrongly still checked
8. The same happens if both setting are checked - they stay checked. If "Move project to Integration Server package as linked resource" is unchecked, on return to the dialog, both settings are unchecked.