Problem
Planning Analytics scheduled chores execute twice instead of executing once as per their defined schedule.
Symptom
- Scheduled chores erroneously executes again exactly after an hour post its defined scheduled run.
- For example if a chore is scheduled to execute at 11 AM Local time,the chore will execute twice once at 11 AM and again at 12 noon.
- Issue only happens when chore is scheduled to run next after a very long duration,for example the chore showcased in the screen-print below is scheduled to run next after 999 days.
Document Location
Worldwide
[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSD29G","label":"IBM Planning Analytics"},"ARM Category":[{"code":"a8m0z000000blsYAAQ","label":"Troubleshooting"}],"ARM Case Number":"","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"All Version(s)","Line of Business":{"code":"LOB76","label":"Data Platform"}},{"Product":{"code":"SSKVSF","label":"Planning Analytics on Cloud"},"Business Unit":{"code":"BU048","label":"IBM Software"},"Component":" ","Platform":[{"code":"","label":""}],"Version":"","Edition":"","Line of Business":{"code":"LOB76","label":"Data Platform"}},{"Product":{"code":"SSCTEW","label":"IBM Planning Analytics Local"},"Business Unit":{"code":"BU048","label":"IBM Software"},"Component":" ","Platform":[{"code":"","label":""}],"Version":"","Edition":"","Line of Business":{"code":"LOB76","label":"Data Platform"}}]
Log InLog in to view more of this document
This document has the abstract of a technical article that is available to authorized users once you have logged on. Please use Log in button above to access the full document. After log in, if you do not have the right authorization for this document, there will be instructions on what to do next.
Was this topic helpful?
Document Information
Modified date:
26 May 2020
UID
ibm16205590