Fixes are available
APAR status
Closed as fixed if next.
Error description
************************************************* The generated command file generated for the Import Journal process is not complete. The two following commands are missing: rpp --rebuildGeneratedLinks --location TEST rpp --synchronizeAllSourceCode --location TEST
Local fix
Create a command file with those 2 lines --rebuildGeneratedLinks --location TEST --synchronizeAllSourceCode --location TEST Then run those commands using the rpp.bat --commands after each MIBJ process
Problem summary
**************************************************************** * USERS AFFECTED: * * All users of the delta migration module * **************************************************************** * PROBLEM DESCRIPTION: * * During delta migration we do not rebuild generation * * generation link and synchronize source code. * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
Temporary fix
Comments
APAR Information
APAR number
PI57274
Reported component name
RATL PROG PATTE
Reported component ID
5725H0300
Reported release
912
Status
CLOSED FIN
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2016-02-16
Closed date
2016-07-22
Last modified date
2016-07-22
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Applicable component levels
R850 PSY
UP
R900 PSY
UP
R901 PSY
UP
R910 PSY
UP
R911 PSY
UP
R912 PSY
UP
[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSKPEG","label":"Rational Programming Patterns"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"912","Line of Business":{"code":"LOB35","label":"Mainframe SW"}}]
Document Information
Modified date:
17 October 2021