Question & Answer
Question
In TRIRIGA, why does my dependency task not go any further than the planned end date if I move the parent task beyond the plan end date?
Answer
The task is that is being moved (along with its dependent task) eventually violates the Planned End Constraint. The task in violation of the constraint is in red and the dependent task will not be moved past the Planned End. If there is no Planned End, there is no constraint and you can freely move both tasks.
[{"Product":{"code":"SSHEB3","label":"IBM TRIRIGA Application Platform"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Component":"--","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"Version Independent","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Was this topic helpful?
Document Information
Modified date:
30 March 2022
UID
swg22005287