Error description
When you have a Craft name with an underscore character in it (for example CRAFT_01) and then run Optimization, the assignments dissappear when Optimization is finished. The assignments can be seen on the Work View tab, and they have been spread out in a manner that looks Optimized, but they are still orange in color signifying that they have not been assigned. We reproduced this in our Maxdemo environment that has all of the LA Fixes we had sent to them for other problems. When I tried it with Planned Labor for a Craft that did not have an underscore in it, there was no problem. Steps to reproduce: 1. Create a Craft with an underscore in the name, such as TEST_CR. 2. Create a new Labor to associate to it. Put it on Calendar/Shift DAY/DAY. 3. Create 3 WO, each with Planned Labor of TEST_CR. 4. In GA create a new Work List 5. Give it Calendar/Shift DAY/DAY 6. Make a Work Query to select the new WO 7. Save 8. Click on the Assignment View tab to view the 3 assignments 9. Create a Labor Assignment scenario 10. Run Optimization - Immediate - Click Submit Now you see the problem. The 3 Assignments dissappear. Click on the Work View tab and you see them on the day you expect to see them but instead of being Orange or Green in color thay are grey. Click Refresh Work List. On the Assignment View the assignments now reappear in Orange on the Craft row meaning they are unassigned (on the Work View tab they change from grey to Orange) . They should have turned Green on the Assignment View tab and been assigned to the Labor.
Local fix
(none) (except don't use an underscore)
Problem summary
**************************************************************** * USERS AFFECTED: * * maximo scheduler users * **************************************************************** * PROBLEM DESCRIPTION: * * IN GRAPHICAL ASSIGNMENT IF CRAFT NAMES HAVE UNDERSCORES IN * * THEM,Optimization result update failed * **************************************************************** * RECOMMENDATION: * * Apply fixpack Release 7.6.1.0 of Base Services or request * * an interim fix * ****************************************************************
Problem conclusion
Fix has been made to fix....The fix for this APAR is contained in the following maintenance package: | release\fix pack\interim fix for Release 7.6.1.0 of Base Services
Temporary fix
Comments
APAR Information
APAR number
IJ03254
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
765
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2018-01-12
Closed date
2018-01-16
Last modified date
2018-01-16
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
R765 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"765","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]