IJ19865: THE PERFORM CRITICAL PATH MAY NOT WORK IF THE USER PROFILE HAS ATIME ZONE THAT DIFFERS FROM THE APPLICATION SERVER TIME ZONE.

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • When the user time zone is different from the applicaiton server
    time zone the perform critical path method button in the
    graphical scheduling application will not work.
    
    
    
    STEPS TO REPRODUCE:
    
    First step is to set a time zone on the user profile that is
    different than the time zone for the application server. Once
    that has been done, log out, back in and then follow steps
    below.
    
    1. Create a work order, add a target start date and end date and
     a duration value.
    
    2. On the plans tab add 4 task, for task 20, add task 10 as it's
    predecessor, for task 30 make 20 it's predecessor and for task
    40 make sure to list task 10, 20 and 30 as it's predecessor.
    
    3. Create a new scheduler record and add the work order created
    earlier, add the shift and calendar as needed and save.
    
    4. Move the graphical view tab, move the first task to a date
    that is later then the last task. Since the last task has the
    first as a predecessor once we press the cpm button the last
    task should be moved to a date later than the new date for task
    10, that does not happen.
    
    
    
    EXPECTED RESULTS:
    
    That the perform critical path button would have provided new
    dates for all the work scheduled as the date of the predecessor
    was moved.
    
    
    Reported in Version:
    
    Tivoli's process automation engine 7.6.1.0 with Maximo Asset
    Management Scheduler 7.6.7.1
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling application in Scheduler   *
    * 7.6.7.                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * THE PERFORM CRITICAL PATH MAY NOT WORK IF THE USER PROFILE   *
    * HAS ATIME ZONE THAT DIFFERS FROM THE APPLICATION SERVER TIME *
    * ZONE.                                                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ19865

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-09-30

  • Closed date

    2019-10-14

  • Last modified date

    2019-10-14

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
14 October 2019