Error description

  • After adding a tool to work order, when we go to Graphical
    Scheduler
    it shows as blue color instead of yellow
    color i.e. availability.
    
    Steps to replicate
    Go to WOT and insert a new work order, Schedule Start
    date=Date_in_the_future
    Schedule Finish date=Same_date_above time=a couple hours later
    than SSD
    Click Plans tab
    Under Tasks enter 2 tasks, 10 and 20, Estimated Duration for
    each task =1:00
    Click on Tools sub-tab
    Click New Row, Task=10, Tool=HAMMER (this is a rotating tool
    with assets) Quantity=1, Tool Hours=1
    Save Record
    
    Go to Graphical Scheduling application and insert new record
    Schedule=1234, Calendar=DAY Org=EAGLENA, Shift=DAY, Duration in
    Days=7
    Work Queries, click new row, Where Condition =
    wonum='your_workorder_above"
    Restrict Resource Availability, click new row, Where Clause=
    1=1,
    Save record
    Click on Graphical View tab
    
    RESULTS: Under Resources the Tool illustration shows BLUE
    
    
    EXPECTED RESULTS: Under REsources the Tool illustration should
    show YELLOW, highlighting availability
    .
    Reported Version Tivoli's process automation engine
    7.6.1.0
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling application in Scheduler   *
    * 7.6.7.                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * TOOL AVAILABILITY COLOR INDICATION DOES NOT DISPLAY IN       *
    * GRAPHICAL SCHEDULING                                         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ18741

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-08-30

  • Closed date

    2019-09-09

  • Last modified date

    2019-09-09

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
09 September 2019