Error description
The problem: when the multiple pos - the receiving of the first po did not update the direct issue and wo pack to to PARTIAL 1. In the Item Master, Create item 'SITEM2', 'SITEM3' - change status to Active . You can use existed items. 2. In the wotrack app, create a new WO (22689 ) In Plan/Materials Tab, add SITEM2 . Tick 'Direct Issue?' add SITEM3 . Tick 'Direct Issue?' Save Approve wo : Then Wo's status will be WMATL. 3. In the Inventory app, Run 'reorder Direct issue itms/svc' for SITEM2,SITEM3. PR 1084 for SITEM2 and 1085 for SITEM3 will be created. 4. go to PR app - open 1084 prnum - approve PR after editing info accordingly. create po 1246 from that PR (select action/create po) open 1085 prnum - approve PR after editing info accordingly. create po 1247 from that PR (select action/create po) 5. go to PO app - open 1246 ponum - Approve it Open 1247 ponum = approve it revise 1247 PO(= revision 1) - change unitcost - approve it. 6. Go to receiving app - Open 1247 -Revision 1 - receive SITEM3 7. Go to wotrack app - open WO (22689 ) - Direct Issue Material Status/Work Package Material Status should be PARTIAL (WRONG !!!) 8. Go to receiving app - Open 1246 PO - receive SITEM2 9. Go to wotrack app - open WO (22689 ) - Direct Issue Material Status/Work Package Material Status become COMP and status is changed to APPR correctly.
Local fix
N/A
Problem summary
**************************************************************** * USERS AFFECTED: * * Users who use the work order direct issue and work pack * * status when receiving direct issue materials for the work * * order but the receipt does not completely satisfy the * * planned materials yet. * **************************************************************** * PROBLEM DESCRIPTION: * * The work order direct issue/work pack status did not change * * to PARTIAL when the po receipt of direct issue items did not * * completely satisfy the planned material. * **************************************************************** * RECOMMENDATION: * * User can upgrade to REL 7.5.0.6 when it is available. Or * * user can request hotfixes. * ****************************************************************
Problem conclusion
This is fixed in code. The fix for this APAR is contained in the following maintenance package: | release\fix pack | Interim Fix for Release 7.5.0.6 Product
Temporary fix
Comments
APAR Information
APAR number
IV50495
Reported component name
WORK ORDERS
Reported component ID
5724R46WO
Reported release
750
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2013-10-07
Closed date
2013-10-10
Last modified date
2013-10-10
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
WORK ORDERS
Fixed component ID
5724R46WO
Applicable component levels
R750 PSY
UP