Fixes are available
APAR status
Closed as program error.
Error description
Large and concurrent update/sync/use/copy_project operations are slowing down a lot and almost giving an impression for the user that the operation has been stuck
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * Synergy users performing large operations * **************************************************************** * PROBLEM DESCRIPTION: * * LARGE AND CONCURRENT UPDATE/SYNC/USE/COPY_PROJECT OPERATIONS * * SLOW DOWN TO GIVE IMPRESSION THAT THE OPERATION HAS BEEN * * STUCK * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
Fixed in 7.2.1.6
Temporary fix
Comments
APAR Information
APAR number
PI84322
Reported component name
TLOGIC SYNERGY
Reported component ID
5724V66SN
Reported release
721
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2017-07-11
Closed date
2017-09-22
Last modified date
2017-09-22
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
TLOGIC SYNERGY
Fixed component ID
5724V66SN
Applicable component levels
R721 PSY
UP
[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSRNYG","label":"Rational Synergy"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"721","Line of Business":{"code":"LOB45","label":"Automation"}}]
Document Information
Modified date:
19 October 2021