Maximo Graphical Assignment "Spatial Scheduling Optimization" Constraints

Troubleshooting


Problem

On running IBM Decision Optimization Center (IDOC) on the Work Order list with "Schedule No Earlier Than" constraint ("Schedule Window?" checkbox ticked), the IDOC does not consider the constraint.

image-20190305134337-1

1) Create a Work Order (WO) with the Scheduled Start Date in the future (2 days ahead).
2) Provide a 'Schedule No Earlier Than' date of 1 day before the Scheduled Start Date (1 day ahead).
3) Create Graphical Assignment including the WO in the Where clause (step 1).
4) Create Spatial Scheduling Scenario on the GA record and click “Run Optimisation”.
5) Navigate to “Constraints” tab on the Spatial Scheduling Optimisation popup window and select “Schedule Window?” (above screenshot).


Symptom

The constraints are not taken into effect unless BOTH “Schedule No Earlier Than“ and “Schedule No Later Than“ dates are specified.

Document Location

Worldwide


[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"Spatial Optimisation","Platform":[{"code":"PF002","label":"AIX"}],"Version":"All Versions","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Log InLog in to view more of this document

This document has the abstract of a technical article that is available to authorized users once you have logged on. Please use Log in button above to access the full document. After log in, if you do not have the right authorization for this document, there will be instructions on what to do next.

Document Information

More support for:
Maximo Asset Management Scheduler

Software version:
All Versions

Operating system(s):
AIX

Document number:
874838

Modified date:
26 March 2019

UID

ibm10874838

Manage My Notification Subscriptions