In the Crews application, by default the Hourly Rate is calculated by the sum of the individual labor rates plus the asset rates that are assigned to the crew.
Content
If Maximo for Utilities is installed, the Hourly Rate is calculated by the average of the individual labor rates instead. This is not optional at the moment.
If you would like the ability to choose the calculation method, you can submit a Request for Enhancement through the link below:
https://www.ibm.com/developerworks/rfe/execute?use_case=submitRfe&BRAND_ID=90
Please use your RFE number to track the progress of your request.
If approved, an RFE can be implemented in a future release of the product.