Question & Answer
Question
What is the formula used to calculate the Earliest Next Due Date (PM.ERLSTWOGENDATE) for PMs?
Answer
The formula for the Earliest Next Due Date is:
If the Target Start = Y then it is PM.LASTSTARTDATE + PM.FREQUENCY
else (Target Start = N) it is PM.LASTCOMPDATE + PM.FREQUENCY
For Meter based PMs:
Units to go = Life to Date next meter reading (not shown in the UI,PMMETER.LTDREADATNEXTWO) - life to date current meter reading (ASSETMETER.LIFETODATE) - Generate wo ahead by (PMMETER.TOLERANCE)
Estimated Next Due Date = Todays date +( Units to go/ASSETMETER.AVERAGE) The estimated due date in PM tab is the earliest of date based and meter based dates.
Was this topic helpful?
Document Information
Modified date:
17 June 2018
UID
swg21689033