Error description

  • This is a follow on APAR to PI54006. (NO WARNING GIVEN WHEN A
    MULTI-PROJECT SYNC USES THE INCORRECT TASK)
    
    That APAR fixed one scenario as documented. There are a number
    of other scenarios where multi project sync does not result in a
    warning if the task is associated with a different release. For
    example:
    
    1. Create Collaborative Project P_a with Release R_a/1 (default
    process rules; possibly an existing Build Management Project
    with corresponding Baseline is required in advance)
    2. Create Collaborative Project P_b with Release R_b/1 (default
    process rules; possibly an existing Build Management Project
    with corresponding Baseline is required in advance)
    3. Create Task 1 with Release R_a/1 and add a dummy text file to
    Project P_a, then check in file and close Task 1
    4. Create Task 2 with Release R_b/1 and add a dummy text file to
    Project P_b, then check in file and close Task 2
    5. Create Task 3 with Release R_a/1 and keep it selected as
    "Current Task"
    6. From outside Synergy client, modify both dummy text files
    7. In the "Projects" list, select both projects P_a and P_b as a
    multi-selection (requires expanding the related "Project
    Groupings" if done using the default "My Project Groupings"
    query) and select "Sync Work Area" > "Members and Subprojects"
    8. In the appearing "Work Area Conflicts" view, select at least
    the dummy file from the "wrong" project (i.e. Project P_b), or
    both dummy files together and select "Keep Work Area Changes".
    
    Expected Results:
    
    An onscreen warning should be issued.
    
    
    This APAR should limit itself to this scenario. All Warnings
    that are provided in a single project sync should also be
    provided in a multi project sync.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * All users that use multi project Sync with different release *
    * values.                                                      *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * No task release warning given when a user perform a multi    *
    * project sync with different release values.                  *
    *                                                              *
    * 1. Create Collaborative Project P_a with Release R_a/1       *
    * (default process rules; possibly an existing Build           *
    * Management Project with corresponding Baseline is required   *
    * in advance)                                                  *
    * 2. Create Collaborative Project P_b with Release R_b/1       *
    * (default process rules; possibly an existing Build           *
    * Management Project                                           *
    * with corresponding Baseline is required in advance)          *
    * 3. Create Task 1 with Release R_a/1 and add a dummy text     *
    * file to Project P_a, then check in file and close Task 1     *
    * 4. Create Task 2 with Release R_b/1 and add a dummy text     *
    * file to Project P_b, then check in file and close Task 2     *
    * 5. Create Task 3 with Release R_a/1 and keep it selected as  *
    * "Current Task"                                               *
    * 6. From outside Synergy client, modify both dummy text files *
    * 7. In the "Projects" list, select both projects P_a and P_b  *
    * as a multi-selection (requires expanding the related         *
    * "Project                                                     *
    * Groupings" if done using the default "My Project Groupings"  *
    * query) and select "Sync Work Area" > "Members and            *
    * Subprojects"                                                 *
    * 8. In the appearing "Work Area Conflicts" view, select at    *
    * least the dummy file from the "wrong" project (i.e. Project  *
    * P_b), or                                                     *
    * both dummy files together and select "Keep Work Area         *
    * Changes".                                                    *
    *                                                              *
    * Actual Result                                                *
    * No warning message about incorrect task release              *
    *                                                              *
    * Expected Results:                                            *
    * An onscreen warning should be issued.                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * N/A                                                          *
    ****************************************************************
    N/A
    

Problem conclusion

  • Fixed in Rational Synergy 7.2.1.5 iFix001
    

Temporary fix

Comments

APAR Information

  • APAR number

    PI60864

  • Reported component name

    TLOGIC SYNERGY

  • Reported component ID

    5724V66SN

  • Reported release

    721

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2016-04-15

  • Closed date

    2016-06-28

  • Last modified date

    2016-06-28

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    TLOGIC SYNERGY

  • Fixed component ID

    5724V66SN

Applicable component levels

  • R721 PSY

       UP