Error description

  • When the queue manager is shutdown, it causes the CHNIT to
    start terminating all its channels, part of that process is
    that the channels attempt to send a network flow to the remote
    partner systems indicating that the queue manager is shutting
    down. However, because the queue manager termination has also
    triggered the CHINIT to implicitly shutdown, it has itself
    requested that no new SSL/TLS channels be allowed to start,
    however this has the effect of blocking any new requests to the
    SSL tasks and prevents the data from being encrypted and this
    failed request results in the CSQX630E message being issued.
    The CSQX630E message that triggered the message in the above
    was caused by a channel . This is a SVRCONN channel that had
    been running previously. It was awaiting requests to be sent
    from the client at the time of queue manager termination. When
    it gets notified of the queue manager termination it attempts
    to let the client know and the SSL communication fails in the
    manner described above.
    To improve this process when the queue manager is terminated
    before the CHINIT, either the channels do not report this
    misleading CSQX630E error or are able to send the queue manager
    quiesce notification to clients.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED: All users of IBM MQ for z/OS Version 9       *
    *                 Release 3 Modification 0 and                 *
    *                 Release 4 Modification 0.                    *
    ****************************************************************
    * PROBLEM DESCRIPTION: CSQX630E 'Channel requires SSL' is      *
    *                      issued when the channel initiator is    *
    *                      terminating.                            *
    ****************************************************************
    During Channel initiator termination, new requests to the
    SSL/TLS server tasks are prevented, causing channels using
    SSL/TLS and attempting to read/write to the socket to fail.
    This behaviour is expected, however the message issued to report
    the error incorrectly indicates that there a problem with the
    SSL/TLS configuration.
    

Problem conclusion

  • CSQX630E is no longer issued due to errors queueing requests to
    the SSL/TLS server tasks during channel initiator termination.
    

Temporary fix

Comments

APAR Information

  • APAR number

    PH63889

  • Reported component name

    IBM MQ Z/OS V9

  • Reported component ID

    5655MQ900

  • Reported release

    300

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2024-10-25

  • Closed date

    2025-07-04

  • Last modified date

    2025-08-02

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

    UO03970 UO03971

Modules/Macros

  • CSQXRSTM
    

Fix information

  • Fixed component name

    IBM MQ Z/OS V9

  • Fixed component ID

    5655MQ900

Applicable component levels

  • R300 PSY UO03971

       UP25/07/12 P F507

  • R400 PSY UO03970

       UP25/07/12 P F507

Fix is available

  • Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.

[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSYHRD","label":"IBM MQ"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"300","Line of Business":{"code":"LOB77","label":"Automation Platform"}}]

Document Information

Modified date:
02 August 2025