IBM Support

JR47928: SNAPSHOTS CANNOT BE INSTALLED TO A PROCESS SERVER THAT WAS SWITCHED FROM ONLINE TO OFFLINE.

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as fixed if next.

Error description

  • When you are installing a process application snapshot, a
    process server that has been switched from online to offline
    is not displayed in the snapshot installation window. This
    error occurs when the process server is stopped and offline to
    Process Center.
    

Local fix

  • 1) Take the online server (PS) offline (as it required for
    upgrade)
    2) Just create new offline server.
    3) Remove the PS in point 1 from server tab.
    4) You need to do step 3 anyway, if you ever wants to bring the
    PS back
    online after upgrade.
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:  IBM BPM administrators                      *
    ****************************************************************
    * PROBLEM DESCRIPTION: Snapshots cannot be installed to a      *
    *                      process server that is stopped and      *
    *                      offline to Process Center.              *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    Process Center receives a shutdown notification from an
    offline process server when the process server is stopped.
    Process Center processes this notification, causing the
    process server to be unavailable for snapshot installation.
    

Problem conclusion

Temporary fix

  • User can manually create a new offline server for offline
    deployment.
    

Comments

  • With the interim fix applied, Process Center ignores process
    server shutdown notifications for offline process servers.
    

APAR Information

  • APAR number

    JR47928

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    801

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2013-09-30

  • Closed date

    2013-10-28

  • Last modified date

    2013-10-28

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

Applicable component levels

  • R800 PSY

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"8.0.1","Edition":"","Line of Business":{"code":"LOB36","label":"IBM Automation"}}]

Document Information

Modified date: