JR46204: PROBLEM IN IDENTIFYING THE LINKS THAT ARE IN CONFLICT

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • integration service with 2 end states(A, B) is referred by
    multiple sub
    services with two end states in a human service.  If change one
    sub
    service output end state
    binding from A to B, the other output end state binding of this
    sub
    service stay and not automatically changed from B to A, so that
    it has
    two ouput end state binding as B. The worse case is that the
    other sub
    services are also impacted, both output state bidnings are
    turned out as
    A.
    

Local fix

  • N/A
    

Problem summary

  • If an integration service has 2 or more end states, and it is
    included 2 times or more in a human service, when the user tries
    to switch the end state bindings, which are in conflict, they
    will observe the links get incorrectly set after the switch.
    
    USER AFFECTED:
    Business Process Manager Advanced, Standard and Express
    authoring users who try to switch the end state bindings, which
    are in conflict, in a human service.
    
    PROBLEM DETAILED DESCRIPTION:
    The problem was a mis-calculation in determining the link that
    is in conflict.  As a result, a different link was picked to be
    switched, and user will see the links incorrectly set.  To avoid
    the problem, delete the end state links that the user wants to
    switch and re-create them accordingly afterwards.
    
    Reproduction steps:
    1. Create a human service, within it create some sub nested
    services.
    2. Build a integration servcice with two end states A and B
    3. Attach above integration service to all sub nested service.
    4. Create two different end states for each sub neted service
    and
    dra
    5. Change on sub service end state binding behavior from B to A
    6. Save service
    

Problem conclusion

  • This APAR will not fix the end state links that are already in
    the incorrect state.  User will have to delete and re-create
    them to correct the problem.  Rather this APAR fixed the Process
    Designer logic in determining the link that is in conflict.  Now
    the end state links switching will work properly after applying
    the APAR.
    
    FIX AVAILABILITY:
    Fix for 8.0.1.1 is available on Fix Central,
    http://www.ibm.com/support/fixcentral/ . Search for APAR JR46204
    
    When downloading the fix package, please ensure the accompanying
    readme is also download, and reviewed thoroughly, for any
    additional info about the fix and install instructions.
    

Temporary fix

Comments

APAR Information

  • APAR number

    JR46204

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    800

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2013-04-02

  • Closed date

    2013-05-30

  • Last modified date

    2013-05-30

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM ADVANCED

  • Fixed component ID

    5725C9400

Applicable component levels

  • R801 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"8.0","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
07 January 2022