A fix is available
APAR status
Closed as program error.
Error description
Migrated BPD instances, which are stopped at an UCA, can not be executed after they are migrated from WLE 7.2.0.2 to BPM 7.5.1. Before migration, there are some BPD instances stopped at an UCA (waiting for trigger condition to next activity). Post migration to 7.5.1, these BPD instances can not be executed any more.
Local fix
n/a
Problem summary
**************************************************************** * USERS AFFECTED: Users migrating from WLE 7.2.0.x to BPM * * 7.5.1. * **************************************************************** * PROBLEM DESCRIPTION: Migrated BPD instances, which are * * stopped at an UCA, can not be * * executed after they are migrated from * * WLE 7.2.0.2 to BPM 7.5.1. * * Before migration, there are some BPD * * instances stopped at an UCA * * (waiting for trigger condition to * * next activity). * * Post migration to 7.5.1, these BPD * * instances can not be executed any * * more. * **************************************************************** * RECOMMENDATION: * **************************************************************** Migrated BPD instances, which are stopped at an UCA, can not be executed after they are migrated from WLE 7.2.0.2 to BPM 7.5.1. Before migration, there are some BPD instances stopped at an UCA (waiting for trigger condition to next activity). Post migration to 7.5.1, these BPD instances can not be executed any more.
Problem conclusion
Problem is fixed in interim fix JR43096. It is also fixed in future fix packs/releases. JR43096 pre-requisites JR42683. Install Instructions: 1. Install JR42683 and JR43096 using Installation Manager 2. Backup the BPM databases 3. On Process Center/Server run upgrade7x using the instructions outlined in http://publib.boulder.ibm.com/infocenter/dmndhelp/v7r5m1/topic/c om.ibm.wbpm.imuc.doc/upgrade/topic/upgrading_existing_dbs_751.ht ml - Perform Step 1 outlined in the above link and along with the parameters mentioned in the above link, pass another parameter for this interim fix. e.g. upgrade_7x.sh -profileName <profile_name> -nodeName <node_name> -serverName <server_name> -ifix JR43096
Temporary fix
Comments
APAR Information
APAR number
JR43096
Reported component name
BPM ADVANCED
Reported component ID
5725C9400
Reported release
751
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2012-06-13
Closed date
2012-08-06
Last modified date
2012-08-06
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
BPM ADVANCED
Fixed component ID
5725C9400
Applicable component levels
R750 PSY
UP