IZ79999: WORK ORDER DURATION NOT BEING UPDATED VIA THE SCHEDULER APPLICATION

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • Problem Details : (Maximo 7.1.1.6; O&G7.1.1.0)
    
    1. Create a Work Order
    2. Add 2 Tasks
    3. Select Predecessors for 2nd task
    4. Create a schedule that will select this Work Order
    5. Notice that both tasks start at the same time initially
    6. Perform Critical Path Method
    7. Now see that the tasks are staggered Finish to Start which
    changes
    the duration of the parent work order in Scheduler. You can see
    this by
    hovering over the work order summary bar and check the duration
    displayed in the tooltips
    8. Save and Commit the changes back to the work order
    
    9. The work order duration of the parent did not get updated and
    written
    back to the work order and the table is not updated
    
    If you now change the duration of one of the tasks by dragging
    the task
    in scheduler, This does update the duration of the parent work
    order
    when committed back to the work order.
    
    Environment :
    Maximo 7.1.1.6; O&G7.1.1.0
    
    Maximo Application : Scheduler, Work Order Tracking
    
    
    Note from Development :
    
    Yes this is a bug. You can create an APAR.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED: Users of Scheduler application.              *
    ****************************************************************
    * PROBLEM DESCRIPTION: Duration field was not updated after    *
    *                      CPM in scheduler app.                   *
    *                                                              *
    ****************************************************************
    * RECOMMENDATION:                                              *
    *                                                              *
    *                                                              *
    *                                                              *
    ****************************************************************
    WORK ORDER DURATION NOT BEING UPDATED VIA THE SCHEDULER
    APPLICATION
    

Problem conclusion

  • Applet was not sending correct duration to server side.
    
    
    
    
    
    The fix for this APAR is contained in the following maintenance
    package:
    
      | release\fix pack | THRASHER
    

Temporary fix

Comments

APAR Information

  • APAR number

    IZ79999

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    710

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2010-07-13

  • Closed date

    2010-11-16

  • Last modified date

    2010-11-16

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R710 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"710","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
16 November 2010