IBM Support

IV78497: STANDARD COST IN CREW TYPE APPLICATION IS NOT GETTING CALCULATED AS DESIGNED

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • Standard Cost in Crew type application is not getting calculated
    as designed,it is taking the average cost
    
    
    Replicated in Maximo 7508 with Utilities/Maximo 760 Utilities
    installed. When you saved a Crew Type that has two Required
    Craft, the Hourle Rate will display the average rate.
    When the second required craft is deleted, the Hourl Rate will
    display half of the rate of the first Required Craft.
    
    MAM 7508, Utiliites  / Maximo 760 Utilites installed
    
    
    Steps to replicate:
    
    
    01) Log into Maximo
    02) Go To Administration > Resources > Crew Types
    03) Click the New Crew Type button to create a new Crew Type and
    fill in the Crew Type name = Test_CT
    04) On the Required Crafts sub-tab, click new row and fill in
    the required fields > Position = Driver , Craft = Test1
    05) Save the record. You will see the hourly rate for the first
    craft as expected.
    06) Add one more craft > Position = Leader, Craft = Test2
    07) Save the record. Now the hourly rate will display the
    average hourly rates of the two crafts.
    08) Delete the second craft that you added and save the record.
    The hourly rate will display half of the hourly rate of the
    first craft.
    Expected results : Step #8 this should show the remaining crafts
    hourly rate
    09) Click again the save button, the record will now display the
    correct hourly rate for the remaining craft.
    
    Note: the behaviour is different when only Base MAM installed.
    Crew Type App when you follow the same above steps the  hourly
    rate is a sum of the crafts added hourly rates not an average,
    and when you deltee craft from crew type, the hourly rate is the
    remaining crafts hourly rate,
    
    AMCrewType/updateStandardRate needs to be fixed: when craft is
    deleted - craft count still considers it calculating an average
    value.
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    
    Tested in base Maximo without any Industry Solution
    installed,
    when there are two Required Crafts in a Crew Type, the Hourly
    Rate will
    display the sum of the two crafts.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Maximo users on 76 using Crews application                   *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * IV78497 STANDARD COST IN CREW TYPE APPLICATION IS NOT        *
    * GETTING CALCULATED AS DESIGNED                               *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply Release 7.6.0.8 of Base Services                       *
    ****************************************************************
    

Problem conclusion

  • Fix logic to calculate standard cost
    

Temporary fix

Comments

APAR Information

  • APAR number

    IV78497

  • Reported component name

    PURCHASING

  • Reported component ID

    5724R46PU

  • Reported release

    750

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2015-11-02

  • Closed date

    2016-12-09

  • Last modified date

    2016-12-09

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    PURCHASING

  • Fixed component ID

    5724R46PU

Applicable component levels

  • R760 PSY

       UP

[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSCHPN3","label":"Purchase Requisitions"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"750","Edition":"","Line of Business":{"code":"","label":""}}]

Document Information

Modified date:
09 December 2016