  • Using the Adapter for Oracle Primavera P6 in Maximo 7.5.0.4 and
    configure it to connect to Oracle Primavera P6 v8.3 are obtained
    errors when importing two or more activities created in a draft
    of Primavera, this project was created by exporting a Workorder
    from Maximo.
    
    Steps to replicate the error:
    
    1. Export a Workorder created in Maximo EAM v.7.5.0.4 to
    Primavera P6 v.8.3
    
    2. Create activities (two or more) in Primavera for project
    described in the item 1.
    
    3. Import everything from the project in the Primavera P6 v.8.3
    to the Workorder linked with Maximo EAM v.7.5.0.4. We want to
    import the activities and tasks .
    
    4. After that, the following exception is presented (one for
    each activity imported) : BMXAA4518E - Another task is already
    using Task 10 .
    
    Level 3 is aware about this PMR and problem and asked  to
    create a new APAR and send this PMR to L3 Development team with
    urgency.
    

Local fix

  • (none)
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Maximo for Primavera Adapter 7.5                             *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * ERROR BMXAA4518E WHEN IMPORTING ACTIVITIES AND TASKS FROM    *
    * PRIMAVERA INTO MAXIMO                                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * No                                                           *
    ****************************************************************
    

Problem conclusion

Temporary fix

Comments

APAR Information

  • APAR number

    IV52928

  • Reported component name

    INTEGRATION

  • Reported component ID

    5724R46I1

  • Reported release

    750

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2013-12-06

  • Closed date

    2013-12-06

  • Last modified date

    2013-12-06

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

Applicable component levels

  • R750 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"750","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]