APAR status
Closed as program error.
Error description
PROBLEM / CLIENT CONCERN: Cannot use the COMPLETE action between Primary and Secondary PM's. Environment ACM 7.1.1.1 Build 20100509-1059 Mobile 7.1.1.0 Scheduler 7.1.1.0 TR 7.1.1.0 BS 7.1.1.6 - LA20100510-1134 - build 20091208-1415 Problem Details: When using the COMPLETE action between 2 PM (one principle and one secondary), generated by 2 Master PMs, if you complete the Main work order, the secondary work order is automatically completed, but the Maintenance Plan for the asset doesn't contain the next event regarding the Main PM. For the secondary PM, the event has been recreated. Maximo Asset Configuration Manager 7.1.1.1-20110222-1608 Build 20100509-1059 DB Build V7121-06 Base Services 7.1.1.6 Build 20091208-1415 DB Build V7116-173 Replication Steps: 1. Go to "Master PM (CM)" 2. Add a new Master PM, with a frequency in DAYS, 15 3. Add a CM Item corresponding to an Asset (CM) 4. Save the record 5. Then, repeat these actions to create another Master PM, for the same CM Item, but with a frequency in DAYS, 30 Master PM (secondary) - screen shot Main Master PM (principle) For this Master PM, in the PM Actions table, add a row using the COMPLETE action, for the secondary Master PM created previously: - screen shot Then, generate the 2 associated PMs using the 'Select Action" > Create Associated PM CM Item The following PMs are created by Maximo (Go To Preventive Maintenance (CM)): SECONDARY PM - screen shot Main PM - screen shot Find the secondary PM, and generate the work order using the 'Select Action' > Generate Work order", untick the Use Frequency tick box. A new work order is generated by Maximo. Go To Asset > Asset (CM) and fing the right assetnum. The click the View Tab > Maintenance Plan sub-tab. Find the Main PM, and modify the Activation Date in the past (2 months ago for instance) in order to have the Due Date in the past. Right-clic on the Asset node in the View tab, and use the BDI Status (Mapping) action in the Contextual menu in order to run the BDI for this asset. A new work order is generated for the Main PM. Go To Work Order > Work Order (CM). Find the work order attached to the main PM, and change the status of the Work Order to COMP (Completed). The work order attached to the secondary PM is automatically completed (working as designed, it is OK). But now, Go To Asset > Asset (CM), and retrieve the Asset associated to the CM Item attached to the PMs : Maintenance Plan As you can see, the event for the Main PM has not been created by Maximo (KO). Asset (CM) > Maintenance History : As you can see, the work orders for the 1004 and 1005 PMs have been completed (the corresponding events are in the history) Screenshots: /ecurep/pmr/3/2/32846,661,706/0-all_data ACTION TAKEN : - Problem replicated. - ACM L3 has authorized APAR creation. ACTION PLAN : Create APAR.
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: Users of Master PM (CM) and PM (CM) with PM * * Actions of type COMPLETE. * **************************************************************** * PROBLEM DESCRIPTION: When a PM Action of type "COMPLETE" has * * been defined between 2 PMs (primary and * * secondary) if you complete the work * * order associated with the primary PM * * the system does not create the next * * Maintenance Event (PLUSALFEVENT) for * * the primary PM. The Maintenance Event * * for the secondary PM is created as * * expected. * * * * Also the Maintenance Event for the * * secondary PM should be marked as * * "CLAIMED" when the associated Work * * Order is completed by the primary. * * * **************************************************************** * RECOMMENDATION: * * * * * * * **************************************************************** Maintenance Event of primary PM is not recreated when Work Order is completed.
Problem conclusion
Code modified to achieve correct behaviour. The fix for this APAR is contained in the following maintenance package: | release\fix pack | Hotfix for Release 7.1.1.2 of Asset Configuration Manager
Temporary fix
Comments
APAR Information
APAR number
IV23783
Reported component name
MX ASSET CONFIG
Reported component ID
5724R4500
Reported release
711
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2012-06-26
Closed date
2012-06-28
Last modified date
2012-06-28
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
MX ASSET CONFIG
Fixed component ID
5724R4500
Applicable component levels
[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSLKSJ","label":"Maximo Asset Configuration Manager"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"711","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]