APAR status
Closed as program error.
Error description
IBM Spectrum Protect Plus backup or restore of Openshift or Kubernetes may hang after the operation is complete. In the job log a message like CTGGA4109 [X.XXX.XXX.XXX] ? Finished backup for k8s agent ? can be observed followed by a sequence of messages like CTGGA2325 [X.XXX.XXX.XXX] Waiting for remote operation to complete on server X.XXX.XXX.XXX The operation also does not complete after cancellation. IBM Spectrum Protect Plus Versions Affected: 10.1.9
Local fix
Restart the IBM Spectrum Protect Plus server. Ensure no other jobs are running when restarting.
Problem summary
**************************************************************** * USERS AFFECTED: * * IBM Spectrum Protect Plus level 10.1.9.x * **************************************************************** * PROBLEM DESCRIPTION: * * SEE ERROR DESCRIPTION * **************************************************************** * RECOMMENDATION: * * Apply the fixing level when available. This problem is * * currently projected to be fixed in IBM Spectrum Protect Plus * * level 10.1.10. * * Note that this is subject to change at the discretion of * * IBM. * ****************************************************************
Problem conclusion
The problem was fixed. The backup and restore operations no longer hang. You can wait for completion or cancel at any time.
Temporary fix
Comments
APAR Information
APAR number
IT39902
Reported component name
SP PLUS
Reported component ID
5737SPLUS
Reported release
A19
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2022-02-07
Closed date
2022-02-16
Last modified date
2022-02-16
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
k8s ocp
Fix information
Fixed component name
SP PLUS
Fixed component ID
5737SPLUS