  • Closed as program error.

Error description

  • After upgrading to IBM Spectrum Protect Plus version
    10.1.6,
    you may experience the maintenance job taking longer to
    
    complete. The duration of the job appears to be dependent
    on
    the resources available to the vSnap because the increase
    in
    time has been from roughly one hour to multiple hours.
    The
    vSnap resources is not the reason for the additional time
    to
    the maintenance job. Adding additional resources only
    masks
    the issue being reported.
    
    The maintenance job runs once
    a day to remove resources and
    associated objects that are
    created by IBM Spectrum Protect
    Plus when a job that is in a
    pending state is deleted.
    
    To see if you encountering this
    issue, review the maintenance
    joblog and check the Summary line
    found at the bottom of the
    log. Reviewing the previous version
    of Spectrum Protect Plus you
    will see something similar to the
    following:
    
    SUMMARY,...,CTGGA2340,Job policy Maintenance
    completed in
    5 min(s) 35 sec(s) and ended with status
    COMPLETED.
    
    After the upgrade to 10.1.6, you will notice a
    significant
    increase is time to complete:
    
    
    SUMMARY,...,CTGGA2340,Job policy Maintenance completed in
    1
    hr(s) 25 min(s) 58 sec(s) and ended with status PARTIAL.
    
    IBM
    Spectrum Protect Plus Versions Affected:
     10.1.6
    
    |MDVREGR
    10.1.6-1971|
    |MDVREGR 10.1.6-1974|
    
    Additional Keywords:
    
    TS003928372 SPP ISPP MAINTENANCE PERFORMANCE
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * IBM Spectrum Protect Plus level 10.1.6                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * See ERROR DESCRIPTION                                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply fixing level when available. This problem is currently *
    * projected to be fixed in IBM Spectrum Protect Plus level     *
    * 10.1.6 iFix3 and 10.1.7. Note that this is subject to change *
    * at the discretion of IBM.                                    *
    ****************************************************************
    

Problem conclusion

  • Reduce the number of calls to the vSnap storage. It may take 2-3
    runs of the maintenance job to return to a normal run time.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IT33781

  • Reported component name

    SP PLUS

  • Reported component ID

    5737SPLUS

  • Reported release

    A16

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2020-08-04

  • Closed date

    2020-08-31

  • Last modified date

    2020-08-31

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    SP PLUS

  • Fixed component ID

    5737SPLUS

Applicable component levels

[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSNQFQ","label":"IBM Spectrum Protect Plus"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"A16","Line of Business":{"code":"LOB26","label":"Storage"}}]

Document Information

Modified date:
31 January 2024