Error description
In Work Order Tracking application whenever WPLABOR is entered, the system updates the Schedule Finish Date same as Schedule Start Date STEPS TO REPRODUCE: 1. Open the Work Order Tracking application and the details for a work order with WAPPR status 2. Check if Scheduled Start and Scheduled Finish dates are filled in. In not select some dates, for Scheduled Finish select a future date, not the current date. 3. Click on Plans tab 4. In sub-tab Labor click New Row: a. Select a Labor b. Effort Hours: 2 c. Click Save 5. Click on tab Work Order the Scheduled Finish Date was updated and it is now the same as Scheduled Start date RESULT: The Scheduled Finish became the same as Scheduled Start date. EXPECTED RESULT: The Scheduled Finish should remain unchanged. REPORTED IN VERSION: Tivoli's process automation engine 7.6.1.3
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * MAXIMO * **************************************************************** * PROBLEM DESCRIPTION: * * SCHEDULED FINISH SAME AS SCHEDULED START AFTER ENTERING A * * PLANED LABOR * ****************************************************************
Problem conclusion
This will be fixed in a future release.
Temporary fix
Comments
APAR Information
APAR number
IJ46175
Reported component name
MAXIMO ASST MGM
Reported component ID
5724R46AM
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2023-03-28
Closed date
2024-06-17
Last modified date
2024-06-17
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO ASST MGM
Fixed component ID
5724R46AM
Applicable component levels
[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSLKT6","label":"Maximo Asset Management"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
17 June 2024