Error description
DESCRIPTION: Child Work Orders generated against the Nested Job Plans doesn't show the relevant items associated with the Job Plan tasks when using the Work Order Organizations level setting- "Process Nested Job Plans in the Background?". STEPS TO REPRODUCE: 1) Go to Organizations; EAGLENA; (i) From More Actions; Select Work Order Options; Other Organization Options; (ii) Deselect the checkbox: "Process Nested Job Plans in the Background?" 2) Create a New Job Plan; Name: JP_NJP3; Description: JP_NJP3 with 1 Material and no JP Task (i) Scroll down and switch to Materials sub-tab; Add a new Item: 0-0031; Storeroom: CENTRAL; Site: BEDFORD; (ii) Save; Change Status to Active 3) Create a new Job Plan; Name: JP_NJP2; Description: JP_NJP2 JP with 1 JP Task having Nested JP & 2 Materials (1 Material at JP level and another at JP Task) (i) Add new Job Plan Task; Task: 10; Description: JP_NJP2- Test Job Plan at Task:10 with Nested Job Plan: JP_NJP3; Nested Job Plan: JP_NJP3 (ii) Scroll down and switch to Materials sub-tab; (a) Add a New Row; Task: 10; Item: 11R22.5GS-9; Storeroom: ATLANTA; Site: FLEET; (b) Add another Row; Item: 27R2.5B26-11; Storeroom: ATLANTA; Site: FLEET; (iii) Save; Change Status to Active 4.a) Create a New Job Plan; Name: JP_NJP1 ; Description: JP_NJP1 - with 1 JP Task having Nested JP & 1 Material (attached to JP Task). (i) Add a new Job Plan Task; Task: 10; Description: JP_NJP1- Test Job Plan at Task:10 with Nested Job Plan: JP_NJP2; Nested Job Plan: JP_NJP2 (ii) Scroll down and switch to Materials sub-tab; Task: 10; Add a new Item: 132-9593; Storeroom: ATLANTA; Site: FLEET; (iii) Save; Change Status to Active 4.b) Optional: Review the Material Item Details added to all the Job Plan and Job Plan tasks (i) JP_NJP3: At Job Plan Level: Material Item: 0-0031; Storeroom: CENTRAL; Site: BEDFORD; At Job Plan Task Level: N/A (ii) JP_NJP2: At Job Plan Level: Item: 27R2.5B26-11; Storeroom: ATLANTA; Site: FLEET; At Job Plan Task Level: Task: 10; Item: 11R22.5GS-9; Storeroom: ATLANTA; Site: FLEET; (iii) JP_NJP1: At Job Plan Level: N/A At Job Plan Task Level: Task: 10; Item: 132-9593; Storeroom: ATLANTA; Site: FLEET; 5) Go to Work Order Tracking Application; Create a WONUM: TESTJP_WO1; Job Plan: JP_NJP1; Save 6) Observe the Result: Switch to Plans tab; (i) There is one WONUM (say 1333) under "Children of Work Order TESTJP_WO1" and No Materials. (ii) Switch to this WONUM: 1333; Under Plans tab, Observe there is another child Work Order with WONUM: 1334 and Description as: JP_NJP2- Test Job Plan at Task:10 with Nested Job Plan: JP_NJP3. Under Materials Tab, this Work Order has 2 Items: 27R2.5B26-11 and 132-9593 (iii) View the WONUM record: 1334; Switch to Plans Tab; Observe there are no child Work Orders and under Materials Tab; we see 2 items: 0-0031 & 11R22.5GS-9 The Child WONUM and Material Items for each Job Plan Tasks are shown here as expected. Reproduce the Issue: 7) Re-test this scenario by enabling the checkbox: "Process Nested Job Plans in the Background?" from the Organizations Application for EAGLENA (i) Enable this option: "Process Nested Job Plans in the Background?" 8) Go to Work Order Tracking Application; (i) Create a WONUM: TESTJP_WO10; Job Plan: JP_NJP1; Save; Refresh the record and see the results at this record. RESULT: Observe the Result: Switch to Plans tab of the WONUM: TESTJP_WO10; (i) There is one WONUM (say 1340) under "Children of Work Order TESTJP_WO1" and No Materials. (ii) Switch to this WONUM: 1340; Under Plans tab, Observe there is another child Work Order with WONUM: 1341 and Description as: JP_NJP2- Test Job Plan at Task:10 with Nested Job Plan: JP_NJP3. Under Materials Tab, this Work Order has ONLY 1 ITEM: 27R2.5B26-11 (iii) View the WONUM record: 1341; Switch to Plans Tab; Observe there are no child Work Orders and under Materials Tab; we see ONLY 1 item: 0-0031 (iv) This shows that the, Work Orders are missing the Material Items associated with the Nested Job Plan tasks. EXPECTED RESULT: (i) In this example, WONUM: 1340 and 1341 should have 2 items in the Materials tab. That is, the Work Orders should have the Material Items associated with the Nested Job Plan tasks. (ii) We should get the same results as obtained when the Organization option: "Process Nested Job Plans in the Background?" is unchecked.
Local fix
N/A
Problem summary
**************************************************************** * USERS AFFECTED: * * MAXIMO * **************************************************************** * PROBLEM DESCRIPTION: * * MATERIAL ITEMS FOR NESTED JOB PLAN TASKS ARE NOT SHOWN AT * * CHILD WO'S WHEN "PROCESS NESTED JOB PLANS IN THE * * BACKGROUND?" IS SET. * ****************************************************************
Problem conclusion
_The fix for this APAR is contained in the following maintenance package: release\fix pack for Release 7.6.1.3 Product._
Temporary fix
Comments
APAR Information
APAR number
IJ35167
Reported component name
MAXIMO ASST MGM
Reported component ID
5724R46AM
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2021-09-27
Closed date
2021-11-29
Last modified date
2021-11-29
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO ASST MGM
Fixed component ID
5724R46AM