Error description
Problem description PM Wogen not copying labour to child work orders when using a nested job plan STEPS TO REPRODUCE: 1. Go to Job Plans Application and Create a new Job Plan "CHILDWO1" Add a description: "Child Work Order Test" Leave all other fields at their defaults and save the record. 2. Change the status of the CHILDWO job plan to ACTIVE 3. Create a new Job Plan PARENTWO1, add a description: "Parent and Child Work Order Test". 4. Under Jon Plan Task Add two tasks to the PARENTWO1 job plan: a. Description: Task 1, Duration: 8:00, Nested Job Plan: CHILDWO1 b. Description: Task 2, Duration: 8:00, Nested Job Plan: CHILDWO1 5. Add two planned labour rows to the PARENTWO1 job plan: a. Craft: ELECT, Qty: 1, Hours: 8, Task: 10 b. Craft: CONSTR, Qty: 1, Hours:8, Task: 20 6. Change the status of the PARENTWO1 job plan to ACTIVE. 7. Create a new PM record "1025" (PM: NESTTEST, Add a description: Nested Job plan Test) a. Select an operating location b. Select the job plan PARENTWO1 c. Select the work type PM d. Set the frequency to 1 and frequency units to DAYS e. Set the Estimated Next Due Date to the current date:03/08/21 8. Save and activate the NESTTEST PM record 9. Go to more actions and Use the Generate Work Orders option to create a new work order ? "1305" > click the plans tab > WorkOrder "1306" genrated for task 1 and "1307" generated for Task 2 UNEXPECTED RESULTS: No planned labour is copied to any of the work orders when using the PM Wogen process. 10.The Parent and Child work orders do not have any planned labour. 11. Create a new Work Order "1309" in Work Order Tracking a. Desc: Manual nested job plan test b. Select an operating location c. Select the PARENTWO job plan 12. Save the Work Order. Child work orders will be generated: WO "1310" generated for Task 1 and "1312" generated for Task 2 a. The Parent work order will not have planned labour b. Child WO 1 (Desc: Task 1) will have 1 planned labour record with Craft: ELECT, Qty: 1, Hours: 8 c. Child WO 2 (Desc: Task 2) will have 1 planned labour record with Craft: CONSTR, Qty: 1, Hours:8 EXPECTED RESULTS: The PM Wogen should process the planned labour to the child work orders in the same way as manually creating the work order using the job plan does. REPORTED IN VERSION: IBM Maximo Asset Management 7.6.1.2
Local fix
Client needs a fix
Problem summary
**************************************************************** * USERS AFFECTED: * * MAXIMO * **************************************************************** * PROBLEM DESCRIPTION: * * PM WOGEN NOT COPYING LABOUR TO CHILD WORK ORDERS WHEN USING * * A NESTED JOB PLAN * ****************************************************************
Problem conclusion
The fix for this APAR will be contained in a future release.
Temporary fix
Comments
APAR Information
APAR number
IJ35130
Reported component name
MAXIMO ASST MGM
Reported component ID
5724R46AM
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2021-09-23
Closed date
2022-09-22
Last modified date
2022-09-22
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO ASST MGM
Fixed component ID
5724R46AM
Applicable component levels
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"Maximo Asset Management"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
22 September 2022