IJ29814: START DATE FOR GRAPHICAL WORK WEEK RECORD IS INCORRECT ONCE CONSTRAINT IS REMOVED AND CPM IS RUN.

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • When a constraint line is removed that connects two task and
    critcal path method (CPM) is run the placement of one of the
    task is incorrect.
    1. Create a work order with 2 child work order, for the child
    work orders add 3 task and add constraints from 10 to 20 and 20
    to 30.  Add a craft for each line, add the other needed
    information and save.
    2. Create a new Graphical Scheduler record and check the more
    information tab to confirm that the preserve scheduled start
    dates is checked.  Add the parent work order and this will bring
    in the children work orders as well as the task and all of its
    dependencies.
    3. On the Graphical View, remove the dependency between Task 10
    and Task 20 under the first child work order, right click,
    delete constraint.
    4. Move the Start Date of Task 20 under the first child
    work order so it does not begin immediately after task 10.
    5. Run CPM for All Rows.  The second child work order moved to
    beginning of first child work order and task 20
    stayed where it was moved.
    6. Repeat these steps and delete the constraint between Task
    10 and Task 20 under the second child work order.
    7. Move the Start Date of Task 20 under the second child
    work order so that it doesn't begin when task 10 ends.
    8. Run CPM on all Rows.  Instead of preserving the Start
    Date of Task 20 under the second
    child work order, it moves the Start Date to align with the
    Start Date of the Child Work Order.
    This is inconsistent with the behavior that I performed for the
    first child work order and not
    what was expected. The Start Date of Task 20 should have been
    preserved since there were no
    constraints and that checkbox was turned for the schedule.
    Reported in Version:
    Maximo Scheduler 7.6.8
    

Local fix

  • n/a
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling application in Scheduler   *
    * 7.6.8.                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * START DATE FOR GRAPHICAL SCHEDULING RECORD IS INCORRECT ONCE *
    * CONSTRAINT IS REMOVED AND CPM IS RUN                         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ29814

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2020-12-11

  • Closed date

    2020-12-15

  • Last modified date

    2020-12-15

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE