IJ18194: SDM - SCHEDULER DATA MANAGER PROBLEM WITH THE RESOURCE TAB NOT CALCULATED CORRECTLY

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM: Scheduler Data Manager problem with the resource tab
    not calculated correctly
    STEPS TO REPRODUCE
    Create new WOT (wo1)
    In Plans tab create the following operations associated with
    the resources:
    OPE10 - Duration 2:00 - craft1 - quantity 1
    OPE20 - Duration 2:00 - craft1 - quantity 1
    Save it
    Crew new GSLP (gslp1)
    Start Date: <today> 12:00 AM
    Duration in Days: 2
    Calendar: DAY
    Shift: DAY
    Work Queries: (wonum like '%wo1%')
    Scenario Allowed?: Unchecked
    Use Alternate Availability? Checked
    Save it
    In Graphical View Tab
    Right Click > Go to Resource Availability
    Make sure a new row is showed for Craft and Crews of this
    Schedule
    Return and Save it
    In SDM go to Resources Tab (Just Available on Aviation 7.6.8
    environement)
    Expected Result: Load Hours is showing craft1 as 4:00
    Actual Result: Load Hours is showing craft1 as 8:00
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Scheduler Data Manager application in Scheduler *
    * 7.6.7.3.                                                     *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * SCHEDULER DATA MANAGER PROBLEM WITH THE RESOURCE TAB NOT     *
    * CALCULATED CORRECTLY                                         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made to address this problem.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ18194

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-08-06

  • Closed date

    2019-08-09

  • Last modified date

    2019-08-09

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
09 August 2019