Error description

  • When a conflict arises on clearance, the application does not
    allow the change of status from RESTORE to RELEASE even
    though there has been an acceptance related to the conflict.
    
    
    Steps to replicate:
    
    1- Create CL 1000, add Tag 1000 on VALVE001, position OPEN.
    2- Move CL 1000 to APPR.
    3- Create CL 1001, add Tag 1001 on VALVE001, position CLOSED.
    4- Move CL 1001 to READY, Accept conflict.
    5- Set Restoration position on Tag 1001 to CLOSED, set
    Restoration sequence.
    6- Move CL 1001 to RESTORE, Accept Conflict.
    7- Try to change CL 1001 status back to RELEASE
    
    RESULT: you get an error message: BMXAK0112E - This status
    change is not allowed.
    EXPECTED RESULT
    
    You should allow the change status and display the
    dialog box for accepting the conflict because Tag 1000 is still
    at DRAFT.
    .
    System info:
    
    IBM Maximo for Nuclear Power 7.6.1.0
    
    Tivoli's process automation engine 7.6.0.8
    
    .
    Application
    Clearances
    .
    Industry Solution
    Nuclear
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * All user of Maximo for Nuclear Power                         *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * USER IS UNABLE TO CHANGE CLEARANCE STATUS FROM RESTORE TO    *
    * RELEASE WHEN A CONFLICT EXISTS BUT HAS BEEN ACCEPTED         *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • Changed the status change process so that it can allow status
    change from restore to release when all possible existing
    conflicts have been accepted.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ17525

  • Reported component name

    MAXIMO FOR NUCL

  • Reported component ID

    5724R5300

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-07-11

  • Closed date

    2019-08-05

  • Last modified date

    2024-10-29

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO FOR NUCL

  • Fixed component ID

    5724R5300

Applicable component levels

[{"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSLL8M","label":"Maximo for Nuclear Power"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
30 October 2024