Error description

  • Once Scheduler 7.6.7 release migrate to the Tree Grid version
    13 we get the format of date columns to decimal instead of the
    date time format as expected.
    Pre Conditions
    - Have some Work Order with Duration, Schedule Start and
    Schedule End Dates
    - Have the Calendar and Shift valid (Not expired and Work
    Period applied)
    Steps to Reproduce
    1-) Go to the Graphical Scheduling application
    2-) Create a new record and setup name, calendar and Shift
    3-) At the Work Queries setup a condition to bring the Work
    Order that you created
    4-) Open the Gantt view tab
    5-) As it open at the Toolbar click at the Export to Excel
    format
    6-) Open the new file created
    PROBLEM: The Date columns at the Excel will get at Decimal
    number, if you apply the Date and Time format at Excel it will
    show as expected.
    EXPECT RESULT: It should get the Date and Time as you saw at
    Maximo Gantt Chart
    

Local fix

  • Apply at Excel the Date and Time format to the Column
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling application.               *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * EXPORT TO EXCEL IS GETTING THE DATE COLUMNS ONDECIMAL NUMBER *
    * INSTEAD OF A DATE FORMAT.                                    *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been delivered.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ03360

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2018-01-17

  • Closed date

    2018-04-30

  • Last modified date

    2018-04-30

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
30 April 2018