IJ01902: DIFFERENT TIMEZONE SHOWS DIFFERENT RESULTS FOR THE SAME WO AND RESOURCES IN GRAPHICAL

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM:  user timezone affects the calculation of planned
    labor hours
    PERFORMANCE ISSUE: N/A
    STEPS TO REPRODUCE:
    1. Login as a user with timezone set to Australia/Brisbane (GMT
    +10 DST/N) Brisbane
    2. Create a work order in Work Order Tracking application  e.g.
    'RES3'
    3.Set the schedule start date to be tomorrow at 10AM (e.g. 10AM
    falls within the 'DAY' shift)
    duration is 10 hours
    select "interruptible"
    select "DAY" as the interruptible shift
    4. Go to the Plans tab, no task work orders
    Enter 2 planned labor:  3 hours for CATER and 10 hours for MUSIC
    5. Go to Graphical Scheduling application, create a new
    schedule e.g.RES3
    Enter a work query to bring up work order 'DUPRES'
    Go to the "Gantt View" tab.
    Gantt Chart shows the interrupt (dark blue color shows the off
    shift hours)
    6. Go to the Resource tab on the bottom
    The available labor is tomorrow which is next available time
    for the labor (e.g. 'DAY' calendar, 'DAY' shift works Monday -
    Friday, 7AM - 3PM)
    NOTE: craft 'MUSIC' has a load of 10 hours and it didn't get
    split over 2 days (this is INCORRECT)
    7. Go to the "Cost and Usage" tab > "Resource Load and
    Availability" tab
    Planned labor hours show 7 hours for Cater and 14 hours for
    Music
    **  This seems incorrect.
    Planned labor hours should show 3 hours for Cater and 10 hours
    for Music (to be spread over 2 days since it's interrupted.)
    8. If I login as user 'wilson'  , timezone is set to
    Canada/Eastern (GMT - 5 DST/Y) Eastern Standard Time, then
    everything shows up correctly
    Bring  up the same Schedule in the Graphical Scheduling
    application
    Go to the Cost and Usage tab > Resource Load and Availability
    tab
    Planned Labor hours shows 3 hours for Cater
    Planned Labor hours shows 8 hours on Nov 15th and 2 hours on
    Nov 16th
    i.e. the labor hours got split due to the 8 hour shift (as
    expected)
    9. If I login as a user that belongs to the New Zealand
    timezone(GMT +12 DST/Y) Auckland, Wellington
    Go to the Cost and Usage tab > Resource Load and Availability
    tab
    Planned Labor hours shows 2 hours for Cater on Nov 15 and 1
    hour for Nov 16 (this is incorrect!  it should not be splitted
    over 2 days)
    planned labor hours shows 2 hours for Music on Nov 15 and 8
    hours for Music on Nov 16 (this is correct)
    10. If I login as user wilson and check the planned labor hours
    from the Cost and Usage tab > Resource Load and Availability
    tab, it will show Planned Labor hours shows 2 hours for Cater
    on Nov 15 and 1 hour for Nov 16 (this is incorrect!  it should
    not be splitted over 2 days)
    planned labor hours shows 2 hours for Music on Nov 15 and 8
    hours for Music on Nov 16 (this is correct)
    NOTE: the planned labor hours used to be correct previously
    when logged in as user wilson
    with timezone set to (GMT - 5 DST/Y) Eastern Standard Time
    CURRENT ERRONEOUS RESULT:   user timezone affects the
    calculation of planned labor hours
    EXPECTED RESULT: user timezone should NOT affect the
    calculation of planned labor hours
    ADDITIONAL INFO: N/A
    ENVIRONMENT (SYSTEM INFO):  TPAE 7.6.0.8
    LOCAL FIX: N/A
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Maximo Users on 7608 or using a specific application         *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Users from 7608 experienced odd results when using GS on     *
    * timezones different from current scheduler tz, this behavior *
    * is not verifiable on later releases                          *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • No changes necessary, the issue is not verifiable on this
    release
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ01902

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    765

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-11-15

  • Closed date

    2017-12-04

  • Last modified date

    2017-12-04

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R765 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"765","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
04 December 2017