Error description
Scenario: 1. Have a big Assembly Checked In. Assembly have many levels. 2. Do Check Out to Assembly with Propagate Operation to all components. 3. Open SolidWorks and Login SMARTEAM. Open Assembly in SolidWorks. ==> Measure time for open is reasonable (e.g. 30 sec). 4. Check In Assembly and all components. 5. Do Open for Edit to some Parts. Modify Parts with SolidWorks. 6. Check In Part and do: Overwrite Previous Revision. 7. Select Assembly and do Check Out. ==> Keep all components as Copy operation. 8. Open Assembly in SolidWorks. ==> KO: Time to open Assembly is not accepted. It may take now about 2 minutes. This is about 400% overhead vs. Assembly with no Modified parts. Notice: Because of steps #5 and #6 Assembly consists with many Modified Components. All Sub-Assemblies are open as Read-Only however they have modified Parts. Open dialog: Show Modified Components and see a very long list of modified components. The more Modified Components you have in list, the longer it takes to open Assembly. Expected: Overhead for this scenario should not be that much. If Assembly consists with hundreds of Sub-Assemblies / Parts and can get up to 600% overhead. This is not accepted by Customer.
Local fix
empty
Problem summary
Scenario: 1. Have a big Assembly Checked In. Assembly have many levels. 2. Do Check Out to Assembly with Propagate Operation to all components. 3. Open SolidWorks and Login SMARTEAM. Open Assembly in SolidWorks. ==> Measure time for open is reasonable (e.g. 30 sec). 4. Check In Assembly and all components. 5. Do Open for Edit to some Parts. Modify Parts with SolidWorks. 6. Check In Part and do: Overwrite Previous Revision. 7. Select Assembly and do Check Out. ==> Keep all components as Copy operation. 8. Open Assembly in SolidWorks. ==> KO: Time to open Assembly is not accepted. It may take now about 2 minutes. This is about 400% overhead vs. Assembly with no Modified parts. Notice: Because of steps #5 and #6 Assembly consists with many Modified Components. All Sub-Assemblies are open as Read-Only however they have modified Parts. Open dialog: Show Modified Components and see a very long list of modified components. The more Modified Components you have in list, the longer it takes to open Assembly. Expected: Overhead for this scenario should not be that much. If Assembly consists with hundreds of Sub-Assemblies / Parts and can get up to 600% overhead. This is not accepted by Customer.
Problem conclusion
THE PROBLEM WAS SUBMITTED ON : I-PLM Collaborative Innovation VERSION V5R19. THIS PROBLEM IS NOT REPRODUCIBLE ON : I-PLM Collaborative Innovation VERSION V5R20 SP7. I-PLM Collaborative Innovation VERSION V5R21 SP2. Additional Closure Information: .
Temporary fix
Comments
APAR Information
APAR number
HE02895
Reported component name
SMARTEAM NT>XP
Reported component ID
569199970
Reported release
519
Status
CLOSED UR1
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2010-12-19
Closed date
2011-10-02
Last modified date
2011-10-02
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
SMARTEAM NT>XP
Fixed component ID
569199970
Applicable component levels
R520 PSN
UP
[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SS2S3T","label":"ENOVIA SmarTeam V5"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"519","Edition":"","Line of Business":{"code":"","label":""}}]
Document Information
Modified date:
02 October 2011