IST2127I
CONNECTIVITY TEST FAILED - NO DIAL OUT LINE AVAILABLE FOR EE

Explanation

A DISPLAY EEDIAG,TEST=YES command was issued to perform an Enterprise Extender connectivity test, but no dial out line was available. At least one EE line associated with the local static VIPA address you are testing must be active and available for use. The EE connectivity test requires an available line to conduct the test even if the connection you are testing has an active EE connection over another EE line.

System action

The DISPLAY EEDIAG,TEST=YES command is not performed.

Operator response

To use the EE connectivity test, perform the following actions to activate an Enterprise Extender line:
  • If EE lines in the EE XCA major node group associated with the local static VIPA address are defined but not currently active, issue a V NET,ACT,ID=groupname,SCOPE=ALL command to activate these lines.
  • If lines were activated, issue the DISPLAY EEDIAG,TEST=YES command again.
  • If no lines are available to perform the EE connectivity test, contact your system programmer.

System programmer response

Update the EE XCA major node to define additional lines that you need to use the EE connectivity test.
  • If you defined a new group with additional lines, the operator can dynamically activate a new group in the EE XCA major node. Issue the V NET,ACT,ID=eexcamajornode,UPDATE=ALL command. See z/OS Communications Server: SNA Operation for more information about using the VARY command.
  • If you defined additional lines to an existing group, activating the new lines might be disruptive to existing EE connections. If this is acceptable, the operator can perform one of the following to activate the newly defined lines:
    • To dynamically update an EE XCA major node group, issue the V NET,INACT,ID=eegroupname,F command to deactivate all existing lines in the modified group. When the EE group is inactive, issue the V NET,ACT,ID=eexcamajornode,UPDATE=ALL command to dynamically update the group. Issue a V NET,INACT,ID=eexcamajornode,F command to deactivate Enterprise Extender. See z/OS Communications Server: SNA Operation for more information about using the VARY command.
    • Issue a V NET,ACT,ID=eexcamajornode,SCOPE=ALL command to activate the modified Enterprise Extender definitions.

When the lines are defined and activated, the operator can issue the DISPLAY EEDIAG,TEST=YES command again.

User response

Not applicable.

Problem determination

Not applicable.

Source

z/OS® Communications Server SNA

Module

You can display the module that issues a SNA message in the message by setting the MSGMOD start option to YES. See Adding the originating module to the message text for more information about the MSGMOD start option.

Routing code

2

Descriptor code

5

Example

None.