After cleaning up information about the old structure, each connector confirms the completion of its cleanup with IXLEERSP EVENT=REBLDCLEANUP. When the system has received the IXLEERSP confirmations from all connectors, the Rebuild Cleanup sync point is reached, the original contoken has been revalidated for each connector, and the Rebuild Process Complete event is delivered to all connectors. |