z/OS MVS JCL Reference
Previous topic | Next topic | Contents | Contact z/OS | Library | PDF


Running a started task under the master subsystem

z/OS MVS JCL Reference
SA23-1385-00

These additional considerations apply to a started task that runs under the master subsystem:
  • Any started task that can operate under the master subsystem can also run under the primary JES subsystem.
  • A started task running under the master subsystem (SUB=MSTR) may choose to use JES services. To do so, the task must issue a Request Job ID call to the JES. (See z/OS MVS Using the Subsystem Interface for additional information about the Request Job ID call.)
  • The started task may include JES statements and commands with the // COMMAND statement. Note, however, that if JES is not running, the system may queue or purge these statements.
  • The JCL may not include a JCLLIB statement.
  • The JCL may include PROC and PEND statements if the JCL is a procedure, but not if it is a job.
  • The started task may not have SYSIN data sets.
  • Start of change The system will initially allocate only data sets that are cataloged in the master catalog or a user catalog. Catalogs must reside on online volumes. End of change
  • You may dynamically allocate data sets that are not cataloged in the master catalog to a task running under the master subsystem during execution.
  • You may dynamically allocate SYSOUT data sets after successfully completing a Request Job ID SSI call.
  • JES exits do not get control during startup processing of a started task. If, however, the started task issues a Request Job ID SSI call, JES exits will get control for the minimal JCL used to construct the JES job structure.
  • SMF exits, such as IEFUJV, get control with the subsystem shown as SYS.
  • SRM determines performance characteristics based on the master subsystem.
  • You may not specify JES3-managed devices in the procedure; JES3 cannot manage devices for tasks that run under the master subsystem.
  • You must code a TIME= value on the EXEC statement of the procedure (such as TIME=NOLIMIT), or else specify the program as a system task in the program properties table (PPT). Otherwise, the task will end abnormally with a time-out condition.
  • You must specify the region size that will be used if REGION is not specified in the JCL.

Go to the previous page Go to the next page




Copyright IBM Corporation 1990, 2014