IBM Tivoli Storage Manager, Version 7.1

Planning the migration

Planning for the migration to Tivoli® Storage Manager V7.1 is important because, in addition to installing the new software, you must move the contents of the V5 server database into the V7.1 server database.

About this task

Tivoli Storage Manager V5 servers can be upgraded directly to V7.1. However, Tivoli Storage Manager V7.1 servers cannot be used with V5 clients or with other servers in the system that are at V5. Unless all V5 clients and V5 servers can be upgraded at the same time, consider upgrading the server to a level that can be used with V5 clients and V5 servers. Then, upgrade all servers and clients to V7.1 when possible. For information about the levels of the Tivoli Storage Manager server that can be used with V5 clients and V5 servers, see the following technotes:

When you move data from a V5 server database to a V7.1 database, a large amount of system processing capacity is used. The move also requires a large amount of I/O activity.

In your planning, consider testing the migration process on nonproduction systems. Testing provides information about how long the migration of the server database takes, which will help you to plan for the time that the server will be unavailable. Some databases might take much longer than others to migrate.

Testing also gives you more information about the size of the new database compared to the original, giving you more precise information about database storage needs.

If you have multiple servers, consider migrating one server first, to determine how the migration process will work for your data. Use the results of the first migration process to plan for migrating the remaining servers.