subscribe iconSubscribe to this information

Moving the system to the installation site

Several factors must be considered before moving the system to the installation site.

Prior to moving the system to the installation site, you should:

For more detailed information, see Access.

If needed, a height reduction feature ( 7960 for ) might be ordered. This feature allows for the system frame and the expansion frame to be shipped in two pieces and assembled at your location. With this feature, the top section of the system frame (including the power subsystem) is removed. The height of the system frame with the upper section removed is reduced by .35 m (14 in.) to approximately 1.64 m (65 in.). For planning purposes, the weight of the rack top frame and components are shown in the following table.

Table 1. Weight of rack top frame and components
  Weight
  lb kg
Bulk Power Assembly (Max value. Varies by Configuration) 179 81.2
Bulk Power Enclosure 45 20.4
Bulk power Controler 10 4.5
Bulk Power Regulator 28 12.7
Bulk Power Distributor 10 4.5
Bulk Power Hub 10 4.5
Side Cover, pair 110 49.9
Front acoustic door, system unit 56 25.4
Rear acoustic door, system unit 36 16.3
Front and Rear Acoustic door, I/O rack 56 25.4
Front and rear slimline door 33 15

Delivery and subsequent transportation of the equipment

DANGER
Heavy equipment—personal injury or equipment damage might result if mishandled. (D006)

You must prepare your environment to accept the new product based on the installation planning information provided, with assistance from an IBM® Installation Planning Representative (IPR) or IBM authorized service provider. In anticipation of the equipment delivery, prepare the final installation site in advance so that professional movers or riggers can transport the equipment to the final installation site within the computer room. If for some reason, this is not possible at the time of delivery, you must make arrangements to have professional movers or riggers return to finish the transportation at a later date. Only professional movers or riggers should transport the equipment. The IBM authorized service provider can only perform minimal frame repositioning within the computer room, as needed, to perform required service actions. You are also responsible for using professional movers or riggers when you relocate or dispose of equipment.