APAR status
Closed as program error.
Error description
PROBLEM: Value that the user enter for Alternate Resource Availability with Dates are getting wrong to the Decision Optimization Server PERFORMANCE ISSUE: NO STEPS TO REPRODUCE: 1-) Create one Record over the Graphical Scheduling application 2-) Add the Work Order Query to push so work to this Schedule 3-) Make sure to check the Alternate Resources over the at More Information tab marked the Scenario Allow and approve the record 4-) Move to the Graphical view 5-)At Resource area right click over an resource and go to Scheduler Alternate Resources 6-) It should by defaul load the quantity as 1 for every resource related 7-) Click at the duplicate line and add the Quantity of 5 for a Week period 8-) Return back to the Graphical Scheduling 9-) Notice the Alternate Resource for this specific work Period 10-) Create a Resource scenario over the More action menu 11- ) Run the optimization CURRENT ERRONEOUS RESULT: The partial value for the week just went over Optimization as a Day EXPECTED RESULT: It should send the Week with Quantity 5 instead of just one day with that. ADDITIONAL INFO: NO ENVIRONMENT (SYSTEM INFO): App Server Weblogic Application Server 12.1.1.0 Version Tivoli's process automation engine 7.6.0.9-IFIX20180330-1643 Build 20171127-0100 DB Build V7609-45 HFDB Build HF7609-04 IBM TPAE Integration Framework 7.6.0.9 Build 20171127-2330 DB Build V7609-32 IBM Maximo Asset Management Scheduler Plus 7.6.7.0 Build 20171127-0100 DB Build V7670-01 IBM Maximo Asset Management Scheduler 7.6.7.0 Build 20171127-0100 DB Build V7670-56 HFDB Build HF7670-12 IBM Maximo Asset Management Work Centers 7.6.0.3 Build 20171121-0723 DB Build V7603-175 Server OS Windows Server 2012 R2 6.3 Server DB Oracle 11.2 (Oracle Database 11g Enterprise Edition Release 11.2.0.3.0 - 64bit Production With the Partitioning, OLAP, Data Mining and Real Application Testing options) (c) Copyright IBM Corp. 2017 LOCAL FIX: N/A SECURITY IMPACT (Y/N): N
Local fix
N/A
Problem summary
**************************************************************** * USERS AFFECTED: * * maximo scheduler users * **************************************************************** * PROBLEM DESCRIPTION: * * Value that the user enter for Alternate Resource * * Availability with Dates are getting wrong to the Decision * * Optimization Server * **************************************************************** * RECOMMENDATION: * * Apply fixpack Release 7.6.1.0 of Base Services (Scheduler * * 7671)or request an interim fix * ****************************************************************
Problem conclusion
Fix has been made to fix....The fix for this APAR is contained in the following maintenance package: | release\fix pack\interim fix for Release 7.6.1.0 of Base Services(Scheduler 7671)
Temporary fix
Comments
APAR Information
APAR number
IJ05596
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
767
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2018-04-09
Closed date
2018-04-17
Last modified date
2018-04-17
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
R767 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
17 April 2018