IJ04370: GA - OPTIMIZATION FAILS WHEN A PARTIAL WORK PERIOD IS SENT WHEN RUNNING SPATIAL DURING A 15 MINUTE WINDOW DURING THE DAY.

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • Opt fails when a partial WP is sent when running spatial opt
    during a 15 minute window during the day. Caused by rounding
    when dividing by resolution minutes, so solution is to remove
    resolution minutes.
    PROBLEM: Optimization fails when a partial WP is sent when
    running spatial opt during a 15 minute window during the day.
    Caused by rounding when dividing by resolution minutes, so
    solution is to remove resolution minutes.
    Pre Conditions
    - Create some Work with Resources need
    - Create a Schedule at the Graphical Assignment application
    that bring those work orders and set the Scenario Allow as true
    - Setup the Decision Optimization to be used
    Steps to Reproduce
    1-) Go to the Graphical Assignment application
    2-) Create a New Labor Scenario
    3-) Run the optimization with the resolution with 15 minutes
    PROBLEM: The Optimization will fail to run
    EXPECT RESULT: The Optimization should be run without the
    resolution in minutes
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * maximo scheduler users                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Optimization fails when a partial WP is sent when            *
    * running spatial opt during a 15 minute window during the     *
    * day.                                                         *
    * Caused by rounding when dividing by resolution minutes, so   *
    * solution is to remove resolution minutes.                    *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply fixpack  Release 7.6.1.0 of Base Services (Scheduler   *
    * 7671)or request an interim fix                               *
    ****************************************************************
    

Problem conclusion

  • Fix has been made to fix....The fix for this APAR is contained
    in the following maintenance package:
    		 | release\fix pack\interim fix for  Release 7.6.1.0 of Base
    Services(Scheduler 7671)
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ04370

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2018-02-23

  • Closed date

    2018-04-17

  • Last modified date

    2018-04-17

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
17 April 2018