Error description

  • PROBLEM:  UNABLE TO RE-SCHEDULE ASSIGNMENT IN GRAPHICAL
    SCHEDULING APPLICATION
    PERFORMANCE ISSUE: N/A
    STEPS TO REPRODUCE:
    - Create new WO record (eg, 1234) for a given Location
    - Enter Target Start date + Target Finish date + Scheduled
    Start date +
    Sched Finish date (all of them for 17 Jan 2018)
    - Enter a Task 10 for this WO.
    - Enter Planned Labor (eg 3 hours)
    - Save and approve the WO
    - Create a new query in Work Order Tracking for this WO (eg,
    WO1234)
    - Go to Graphical Scheduling
    - Create a new record with Type=WORK with a Calendar + Shift
    - Go to Work Queries and  Copy Query  and select the query
    created above
    - Go to the Gantt View tab
    - The rows for the Task WO and main WO show Start/ End date =
    17 Jan
    2018
    - Check box for that Task WO row and right-click on Description
    field
    - Select Reschedule/Unassign Assignments
    - Change date to 20 Jan 2018 ( Reschedule the
    assignments?  is
    checked by default)
    - The rows for the Task WO and main WO now show Start/ End date
    = 17
    Jan 2018
    - Select Action / Commit Changes
    - Go to Work Order Tracking and select the same WO created
    previously
    - The Target Start date + Target Finish date + Scheduled Start
    date +
    Sched Finish date fields all still show 17 Jan 2018.
    - Go back to Graphical Scheduling
    - Set  Preserve Schedule Start Dates?  field to unchecked
    - Go to Gantt View and change the date for the Task WO row to
    22 Jan
    2018 ( Reschedule the assignments?  is checked by default)
    - The rows for the Task WO and main WO now show Start/ End date
    = 22
    Jan 2018
    - Select Action / Commit Changes
    - Go to Work Order Tracking and select the same WO created
    previously
    - The Target Start date + Target Finish date + Scheduled Start
    date +
    Sched Finish date fields all still show 17 Jan 2018
    CURRENT ERRONEOUS RESULT:  unable to re-schedule assignment.
    start and end dates do not get updated in the "Graphical View"
    tab.  For existing schedule, re-scheduling assignment do not
    update duration
    EXPECTED RESULT:  should be able to re-schedule assignments
    ADDITIONAL INFO: N/A
    ENVIRONMENT (SYSTEM INFO):
    Tivoli's process automation engine 7.6.0.7 Build 20170215-0100
    DB Build
    V7607-14
    IBM Maximo Asset Management
    Scheduler 7.6.4.0 Build 20170215-0100 DB Build V7640-53
    LOCAL FIX: N/A
    SECURITY IMPACT (Y/N): N
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling application in Scheduler   *
    * 7.6.7                                                        *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Re-scheduling assignments in Graphical Scheduling does not   *
    * move parent WO dates.                                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • This feature was redesigned and a code change has been
    delivered.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ03713

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2018-01-29

  • Closed date

    2018-02-05

  • Last modified date

    2018-02-05

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
05 February 2018