IJ01302: IN GRAPHICAL ASSIGNMENT RUNNING OPTIMIZATION USING THE AT THIS TIME OPTION DOES NOT WORK, IT NEVER RUNS.

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • In  Graphical Assignment (GA) when Running Optimization using
    the At This Time option on the Spatial Scheduling Optimization
    dialog box, the optimization never runs.
    
    As Optimization can take some time it is useful to run it at a
    future time instead of immediately, which is why we have to
    option to run it At This Time and you then specify a date/time
    to run the optimization.
    
    In GA running on 7608 with the latest IFix at 2:52pm I asked it
    to run at 3:15pm but it is now almost 4pm and the optimization
    has never run.
    Just before doing this I ran it Immediately and it finished
    successfully and took about 1-2 minutes.
    
    I reproduced this on 7.6.0.8 with the latest IFix.
    I also reproduced it on a 7.6.0.9 environment with Optimization
    set up.
    
    This was in GA, it appears to run ok in GS.
    
    STEPS TO REPRODUCE:
    
    1. Create a Work List in Graphical Assignment with several WO,
    each with at least one Planned Labor row.
    2. Use a Calendar and Shift, such as Day/Day, that is also
    assigned to some of the Labor assigned to the Crafts used by
    the WO.
    3. Save the Work List.
    4. Confirm that Configure Optimization server has been set up
    and that Workassign has been deployed.
    5. Create a Spatial Scheduling Scenario.
    6. Open the Run Optimization dialog
    7. In the Schedule section select the At This Time option.
    8. Enter a time at least 15 minutes in the future.
    9. Enter an email address for the notification.
    10. Click on Save.
    11. Open the View Scheduled Optimization Processes dialog box
    and you  will see the one you just submitted listed for the
    time you  selected.
    
    And that is the problem, it never leaves that dialog.   It
    should leave the  View Scheduled Optimization Processes dialog
    box and then be viewable on the  View Optimization Processes
    dialog box where you can see it listed as having processed at
    the time you selected.
    

Local fix

  • (none)
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * maximo scheduler                                             *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * In  Graphical Assignment (GA) when Running Optimization      *
    * using                                                        *
    * the At This Time option on the Spatial Scheduling            *
    * Optimization                                                 *
    * dialog box, the optimization never runs.                     *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply fixpack  Release 7.6.0.9 of Base Services or request   *
    * an interim fix                                               *
    ****************************************************************
    

Problem conclusion

  • Fix has been made to fix....The fix for this APAR is contained
    in the following maintenance package:
    		 | release\fix pack\interim fix for  Release 7.6.0.9 of Base
    Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ01302

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    765

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-11-06

  • Closed date

    2017-11-08

  • Last modified date

    2017-11-08

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R765 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"765","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
08 November 2017