IJ01159: INCORRECT DURATION AFTER RESIZING THE TIME BAR IN GRAPHICAL SCHEDULING

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM:  incorrect duration after resizing the time bar in
    Graphical Scheduling
    
    PERFORMANCE ISSUE: N/A
    
    STEPS TO REPRODUCE:
    
    CURRENT ERRONEOUS RESULT:
    STEPS TO REPLICATE:
    1. Go to the Calendar application, bring up Calendar 'DAY'
    work period for DAY shift is 7AM - 3PM
    
    2. Go to the Labor application
    bring up Labor 'wilson'
    calendar is 'DAY' and shift is 'DAY'
    Go to the Crafts tab
    craft is 'ELECT' and skill level is 'FIRSTCLASS'
    ensure that labor has a status of 'ACTIVE'
    
    3. Go to work order Tracking application
    create a work order 'MAY02'
    enter scheduler start 10/8/17 7:00 AM
    enter 7:00 in the duration field
    Go to the Plans tab
    click New Row button to enter a task
    Enter task 10 with 2 hours duration
    click New Row button to enter another task
    Enter Task 20 with 3 hours duration
    Go to the Labor sub-tab on the bottom
    click New Row button to a planned labor usage
    Task 10, craft 'ELECT', LABOR 'wilson' ,skill Level
    'FIRSTCLASS',
    quantity=1, regular hours=2:00
    click New Row button to enter another planned labor
    Task 20, craft 'ELECT', LABOR 'wilson' ,skill Level
    'FIRSTCLASS',
    quantity=2, regular hours=3:00
    Save
    
    4. Go to Graphical Scheduling application
    create a new schedule
    Calendar 'DAY' for Organization 'EAGLENA'
    Shift 'DAY'
    Type 'WORK'
    start date 10/8/17 12:00 AM
    end date 10/18/17 12:00 AM
    Go to the Work Queries
    Enter a new Row
    Data Source = WORKORDER
    where condition:    wonum='MAY02'
    Save
    
    5. Go to the "Gantt View" tab
    Duration field for the work order 'MAY02' shows 7 hours
    (note: duration is a field added to TPAE 7608)
    Duration field for Task 10 shows 2 hr
    Duration field for Task 20 shows 3 hr
    
    resize the time bar for task 20 to the right to increase it to
    4 hours
    save
    
    Duration field now shows 4 hours (CORRECT)
    
    resize the time bar for task 20 to the left to decrease it to 2
    hours
    save
    
    Duration field now shows 2 hours (CORRECT)
    check the Duration field for the main work order
    the duration for the main work order has changed from 7 to 2
    (INCORRECT)
    the time bar for the main work order has also shrunk to 2 hours
    
    unable to resize the time bar on the parent work order to
    increase the
    duration to 7
    attempt to increase the length of time bar for  task 10 by
    resize it
    to the left
    let go of the mouse when it reaches 5AM in the morning
    the time bar disappeared for task 10 (it became a grey dotted
    diamond
    instead of a bar)
    
    Duration for the main work order and task 10 now shows 0
    (INCORRECT)
    Duration for task 20 now shows 2 (INCORRECT)
    
    EXPECTED RESULT: Duration field from the Gantt View should be
    in sync with the time bar after resizing the time bar
    
    ACTUAL RESULT: Duration field from the Gantt View should be in
    sync with the time bar after resizing the time bar
    
    ADDITIONAL INFO:  replicated in TPAE 7.6.0.8 for the newly
    added Duration field
    
    ENVIRONMENT (SYSTEM INFO):  TPAE 7.6.0.8 Scheduler 7.6.5
    
    LOCAL FIX:  N/A
    
    SECURITY IMPACT (Y/N): N
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Duration column not updated in real time when you resize the *
    * gantt bar.                                                   *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • Fixed
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ01159

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    765

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-11-01

  • Closed date

    2017-11-02

  • Last modified date

    2017-11-02

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R765 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"765","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
02 November 2017