Ensuring that all installation tasks are complete
Make sure that you have:
- Created a started-task procedure for the Z controller
- Allocated data sets
- Given security authority to the started task to access its data sets
- Specified the initialization statements in the parameter library (EQQPARM)
- Included the Z controller in an XCF group, if it uses an XCF connection
- Defined a VTAM® application ID for the Z controller and activated the VTAM resources, if it uses an NCF connection
- Updated SYS1.PARMLIB and defined VTAM resources, if users communicate with the Z controller through the IBM Z Workload Scheduler API or if the IBM Z Workload Scheduler server is used.
- Set up the ISPF environment for IBM Z Workload Scheduler dialog users.