Verifying job submission
When IBM Z Workload Scheduler submits
work, a submit event is written to the event
data set. A submit event is prefixed with an I, and can be one of
these:
- IJ1
- Job JCL. A job has been submitted.
- IJ2
- Started-task JCL. A started task has been started.
- IWTO
- An operation has been initiated for a general workstation with the WTO option. The submit task causes message EQQW775I to be issued.
To
perform this test for all type I events, start an operation
on each of three workstations, all of which specify the destination
of the system you are testing. The workstations must be a computer
automatic workstation for IJ1 events, a computer automatic workstation
with the started-task option for IJ2 events, and a general WTO workstation
for IWTO events. Follow this procedure to verify workload submission:
- Ensure that you have the correct workstations specified in the workstation description database.
- Create a test application with an operation for each workstation you want to test, and add it to the current plan.
- When the application has completed, browse the event data set, and verify that the required type I events have been created.
- If the operations are not started, check that the workstation status is ACTIVE and that the workstation is not WAITING FOR CONNECTION, which means that the Z controller is waiting for the corresponding tracker to communicate.